East End Water Infrastructure Project

September 22, 2025

Crews will be working along Washington Street between Alvasia Street and Ingram Street repairing street cuts and locating existing utilities. The intersection of Washington Street and Ingram Street will be closed at times. 

July 28, 2025

Starting Tuesday, July 29th, Henderson Water Utility’s contractor, Deig Brothers Construction, will begin work along Washington St. between Green St. and Alvasia St. This is a continuation of a project that started last October to replace our aging water and sewer infrastructure on the east end of Henderson. Construction is expected to last through October.

Residents and businesses may experience temporary interruptions to their water and sewer services. They can anticipate construction activities near their homes and businesses, and they will encounter temporary disruptions to street access and parking.